Previous fitment of Shanghai Eton Hotel completed and files accepted

Published:2006-08-12


Until July, 85% of fitment construction of guest rooms in Eton Hotel was completed, 60% of fine fitment of floors 34 to 36 for executive uses was completed, 40% of the fine fitment of the entrance hall on the first floor was completed and 45% of fine fitment of floors 3 to 5 in the skirt building was completed. In addition, the central garden construction of the hotel is adjusted; kitchen fitments of the hotel has now been transported to the site and installed partially. The hotel has currently recruited 485 employees, who are now receiving training and is being prepared for the trial operation in the beginning of Oct.